A wood and charcoal bench beside a curving path and open lawn in a quiet late-autumn Minnesota neighborhood park.

What's Drawn Into West St. Paul's New Park at 150 Thompson, and What Could Still Change

November 12, 2026

Sheet L010 of a drawing set dated October 27, 2026 calls for 1,310 square feet of tan bunker sand, nine inches deep over geotextile fabric, for a new park in West St. Paul. The sand is listed as "USGA spec," the grade used in golf course bunkers. Elsewhere in the set are 1,770 square feet of golden oak composite boardwalk on helical piles, a bandshell stage, nine 18-foot light poles strung with catenary lights, and a building with four restrooms.

All of it is planned for the southeast corner of 150 Thompson Avenue, the former YMCA site. The city describes the 2.48-acre park as a community gathering space with views of the pond, on the River-to-River Greenway with the library nearby. These drawings are the most detailed version of the park so far. They also come right before the step the city expects may cut them back.

The Concept Turned Into a Parts List

In September, the West St. Paul Reader described the concept in broad terms: an amphitheater and open lawn for events, a picnic shelter, a play area, an urban beach, a splash feature, and restrooms. Seven weeks later, the 90% schematic set turned those ideas into specific products with quantities attached.

Here is what the materials and furnishings schedules list:

  • The stage. A bandshell stage, with a stage-loading area marked on the plan.
  • The water's edge. An elevated boardwalk of Millboard composite decking over a steel structure on helical piles, plus 78 linear feet of boardwalk stairs.
  • The beach. The 1,310 square feet of bunker sand that makes the "urban beach" real.
  • The splash pad. It has decorative concrete around it, but the schedule notes the pad itself is "to be designed by others."
  • The playground. Poured-in-place rubber surfacing in a custom lilac purple, with plum accents and a rubber-covered mound.
  • The play pieces. Two A-frame "alpine huts" and a six-seat discovery table, both in Alaskan yellow cedar, plus a set of tube chimes, a triple hammock stand, and four salvaged tree trunks six to twelve feet long.
  • The places to sit. Eleven picnic tables in turquoise blue and Nordic pine, 481 linear feet of concrete seat walls, 38 large glacial fieldstone boulders, and six marine-grade umbrellas.
  • The art. A concrete pedestal for rotating art provided by the city.
  • The lighting. Nine catenary light poles, eight area lights with built-in speakers, and six path bollards.

Paths are drawn in stabilized crushed marble in a beige blend, with decorative concrete in the gathering areas. Area lights with speakers and catenary lighting over a stage are what you install for evening events.

A Building With a Community Room

The architectural sheets, by U+B Architecture & Design, go past the "restrooms" in the concept. The floor plan shows four restrooms, a lobby, a maintenance room, storage, a mechanical room, a garbage room, and a community room. One layout fits 40 chairs, and another fits six 72-inch rectangular tables.

That room changes what kind of park this is. With an indoor room, a restroom building, and a stage outside, the park could host a meeting, a party, or a small event in a month when nobody is using the splash pad. The building is also one of the items the coming pricing will put a number on.

Why the November 10 Review Carries More Weight Than the Ones After It

On Tuesday, November 10, the Parks & Rec Advisory Committee was scheduled to review the 90% plans, presented by Parks and Recreation Director Eric Weiss. The staff memo for that meeting is unusually direct about why this point counts. It says the completion of schematic design "is a critical design stage," and that "as we move into further planning phases, it becomes more difficult – and expensive – to reconfigure plans."

The memo also sets out the order of events. Once schematic design is finished, the project team will get high-level pricing that includes several project alternatives, and "from there, we will be able to determine budgets, phasing, and project trade-offs, if necessary." It names value-engineering and project phasing as things the city may need to consider.

The committee was asked to come ready to discuss four questions:

  1. Overall Design: Does the plan reflect what you have heard from the community? Is anything missing or out of place?
  2. Feature Areas: What works well? What would you change?
  3. Uniquely WSP: Does this plan match the city's vision outlined in the Branding+Placemaking Roadmap and Parks System Plan?
  4. Phasing and Budget: If costs require trade-offs, what is a priority, what can wait, and what matters most to protect?

The fourth question is the one for anyone following the park. The city is already asking what could wait, before any prices are back.

The Gap the Prices Will Land On

The money explains why that question came early. According to the West St. Paul Reader, when the City Council approved the project last December, park funding was $5 million to $7 million short. The state has since offered $1 million. City Manager Nate Burkett has proposed closing the rest from multiple sources, and as of September the Council had not formally approved that approach.

Phasing is the most likely way the plans and the budget meet in the middle. The park the drawings describe and the park that opens first may not be the same. A playground and lawn can open while a building or a splash pad comes later. Which pieces go into a first phase is exactly what the committee was asked to rank.

The park also sits inside a larger project with its own schedule. Here is how the full 11-acre site lines up, based on the September reporting:

Piece of 150 Thompson What it includes Target timing
Retail Rehabbed 7,100-sq-ft former AutoZone building with a sit-down restaurant and other retail; no restaurant identified End of 2027
Townhouses 19 rental townhouses completing the existing development on Crawford Drive End of 2027
Park 2.48 acres in the southeast corner, facing the pond Hoped for by summer 2028
First apartment building Five stories, part of 457 market-rate units across two buildings 2028
Second apartment building Construction starts after the first; possible completion by 2030 Possibly 2030

The Reader reports that the overall timeline slipped by about a year. The total project cost is around $145 million, with nearly $20 million in tax increment financing approved over two phases. Site work started in September, almost seven years after the YMCA closed. The city buying the property is what made a public park and a sit-down restaurant part of the deal.

For people living near Thompson, Robert Street, and Crawford Drive, the construction comes with a tree count. The project removes 156 quality trees and replaces them with at least 217 new ones. A tree preservation plan is part of the park drawing set.

How the Plans Got Here, and Who Drew Them

The design team is led by Damon Farber Landscape Architects, with U+B Architecture & Design on the building and Pierce Pini & Associates on civil engineering. The city memo lists four rounds of input behind this version: a September 8 committee design workshop, a pop-up at the Night Market, an online survey, and a September 29 community open house. It adds that the plans have kept changing based on committee, Council, and staff input, community feedback, and "budget and cost considerations."

That Night Market tied the new park to an older one. It was held at the refurbished pavilion at the West St. Paul Sports Complex, 1650 Oakdale Avenue, where the city removed the horseshoe pits and fencing earlier this year to open the covered space for other uses. Weiss told the Reader the change responded to calls for more events, programs, and festivals. He named family reunions, cultural events, markets, and park music as possible uses. The 150 Thompson drawings plan for the same kinds of events with more built in: a stage, lighting with speakers, and a room with restrooms next to it.

The city memo ties the project to its strategic goal of maximizing use of public amenities and "third spaces," and to the Park System Plan's goal of creating "new, unique gathering spaces." The committee memo and the full 90% drawing set are posted in the city's agenda center for anyone who wants to read the sheets themselves. The next public milestone is the pricing, along with whatever list of alternatives comes with it.

At The Distad Team, we read schematic sets like this all the time through our work at Hilltop Development, and we know how much changes between 90% drawings and opening day. If you own a home near Thompson Avenue or the Greenway and want to talk through what this park and the rest of 150 Thompson could mean for your block, we're happy to go through the plans with you. Schedule a Consultation.

Partner With Us

Ready to get started? Reach out today and take the first step toward achieving your real estate goals!